Which of the following describes the project status?

The project schedule performance index is 1.1, and the cost performance index is 0.9.

Which of the following describes the project status?
A . Ahead of schedule and over budget
B . Behind schedule and under budget
C . Ahead of schedule and under budget
D . Behind schedule and over budget

Answer: C