A program manager at a pharmaceutical company plans a new drug development effort. The development is slated to yield three drug variants. The program manager articulates the program scope boundaries.
Which of the following deliverables captures these items?
A . Program scope management plan
B. Program governance plan
C. Program scope statement
D. Program work breakdown structure
Answer: C