Which of the following could MOST likely be the cause of this issue?

A financial manager reports that several employees’ allocations from the past month appear to be 200% even though they are only assigned to a particular project.

Which of the following could MOST likely be the cause of this issue?
A . A project manager assigned the wrong resources.
B . A project manager did not release the resources
C . A project manager did not remove the system access.
D . A project manager did not provide the project sign-off.

Answer: B

Explanation:

A project manager did not release the resources. A project manager not releasing the resources could most likely be the cause of this issue where several employees’ allocations from the past month appear to be 200% even though they are only assigned to a particular project. Releasing resources is a process of freeing up or reallocating any human or material resources that were used for a project after its completion or closure. Releasing resources can help to update the resource availability and utilization records and avoid any conflicts or errors in resource allocation or reporting.

Latest PK0-005 Dumps Valid Version with 81 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments