Which of the following could be useful to an organization that wants to test its incident response procedures without risking any system downtime?
Which of the following could be useful to an organization that wants to test its incident response procedures without risking any system downtime?
A . Blue team exercise
B. Business continuity exercise
C. Tabletop exercise
D. Red team exercise
Answer: B
Explanation:
Reference: https://www.gsma.com/mobilefordevelopment/wp-content/uploads/2017/11/Exercising-BC-Plans- for-Natural-Disasters-A-Quick-Guide-for-MNOs.pdf