Which of the following constraints does this impact MOST?
A non-stakeholder approaches the project manager and asks if certain items can be added
to a project that was started two months earlier.
Which of the following constraints does this impact MOST?
A . Time
B . Schedule
C . Scope
D . Cost
Answer: D