Which of the following constraints does this impact MOST?
A non-stakeholder approaches the project manager and asks if certain items can be added to a project that was started two months earlier .
Which of the following constraints does this impact MOST?
A . Time
B . Schedule
C . Scope
D . Cost
Answer: D
Latest PK0-004 Dumps Valid Version with 574 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments