Which of the following considerations is important when planning the low-level design of a data center solution to ensure high availability?
A . Software licensing agreements
B . Network monitoring tools
C . Backup power source
D . Data encryption protocols
Answer: C
Explanation:
Having a backup power source is essential for ensuring high availability in a data center solution, reducing the risk of downtime due to power outages.