Exam4Training

Which of the following communication methods should the project manager use?

A project manager prefers to have immediate contact with team members because it allows for faster response times and more interactive discussions.

Which of the following communication methods should the project manager use?
A . Synchronous
B . Informal
C . Asynchronous
D . Formal

Answer: A

Explanation:

The project manager should use synchronous communication methods if they prefer to have immediate contact with team members. Synchronous communication is a type of communication that occurs in real time and allows for faster response times and more interactive discussions. Examples of synchronous communication methods include phone calls, video conferences, instant messaging, and face-to-face meetings. Synchronous communication can help to build rapport, clarify doubts, and resolve issues quickly among team members.

Synchronous communication should be used when the project manager prefers to have immediate contact with team members. Synchronous communication allows for real-time interaction and feedback, enabling faster response times and more interactive discussions.

Reference: CompTIA Project+ Study Guide Section 3.1.3

Latest PK0-005 Dumps Valid Version with 81 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Exit mobile version