Which of the following charts would indicate the cause and effect of tasks in a project, and for which of the following activities would the chart be used?
Which of the following charts would indicate the cause and effect of tasks in a project, and for which of the following activities would the chart be used?
A . Histogram, forecasting
B . Ishikawa, quality control
C . Scatter, determining resources
D . Gantt, leveraging resources
Answer: B