Which of the following charts should the PM include in the status report?

The PMO has asked the PM to provide a status report indicating the number of events and activities required to complete a project .

Which of the following charts should the PM include in the status report?
A . Gantt chart
B . Scatter chart
C . Run chart
D . Process diagram

Answer: A