You are managing a portfolio in a functional organization and resources are shared between operations and projects. You are continuously performing capability and capacity analysis in order to optimize the portfolio .
Which of the following capability and capacity analysis is used to limit the number OR size of components the organization can execute?
A . Knowledge Basis
B . Financial
C . Human Resources
D . Assets
Answer: B