Which of the following can you use to prevent the external procurement of certain materials? Note: There are 2 correct Answers to this question.

Which of the following can you use to prevent the external procurement of certain materials? Note: There are 2 correct Answers to this question.
A . Material status
B. Requirements group
C. Material group
D. Material type

Answer: C,D