A PM wants to provide a visual representation of how a project is organized into tasks and how the tasks relate to each other.
Which of the following can the PM use?
A . Milestone chart
B . Gantt chart
C . PERT chart
D . WBS
Answer: B
Explanation:
A gantt chart is a visual representation of a project timeline that shows the tasks, durations, dependencies, and resources of a project in a horizontal bar chart format. A gantt chart can help a project manager to plan, monitor, and control the project progress, scope, and quality. A gantt chart is different from a milestone chart, which only shows the key events or deliverables of a project without the details of the tasks. A gantt chart is also different from a PERT chart, which is a network diagram that shows the logical relationships and sequence of tasks in a project. A gantt chart is also different from a WBS, which is a hierarchical breakdown of the project scope into smaller and manageable components.
Reference = CompTIA Project+ Study Guide: Exam PK0-005, 3rd Edition, Chapter 6: Schedule Management1; CompTIA Project+ Certification Study Guide, 3rd Edition, Chapter 6: Schedule Management2; What Is a Gantt Chart? 7 Examples for Project Management3; 3 types of visual project management: Timelines, calendars, and boards (with examples)4
Latest PK0-005 Dumps Valid Version with 81 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund