Which of the following can be done to control the size of the Project Board on a project that involves multiple users and suppliers?
A . Create a separate Project Board to manage the supplier elements of the project
B . Create multiple smaller Project Boards during the process of Starting up a Project, one for each of the project’s stages.
C . Create user and supplier groups
D . Appoint corporate quality assurance to perform the Project Assurance role for all members of the Project Board
Answer: C
Explanation:
To control the size of the Project Board on a project that involves multiple users and suppliers, creating user and supplier groups is an effective strategy. These groups can represent broader interests and provide input to the Project Board, helping to streamline decision-making processes without overloading the board with members.
Reference: PRINCE2 Foundation manual, PRINCE2 official resources