Which of the following can be determined?
An active project has a CPI of 0.92 .
Which of the following can be determined?
A . The project is currently over budget.
B . The project has a budget surplus.
C . The project is ahead of schedule.
D . The project is behind schedule.
Answer: A
Explanation:
Reference http://smallbusiness.chron.com/project-management-cpi-numbers-mean-35541.html