Which of the following can be adjusted during a time box? 1) Scope 2) Resource 3) Time 4) Quality

Which of the following can be adjusted during a time box? 1) Scope 2) Resource 3) Time 4) Quality
A . 1 and 2 only
B . 1 and 4 only
C . 3 and 4 only
D . 2 and 4 only

Answer: B