Which of the following BEST indicates the effectiveness of an organization’s risk management program?
Which of the following BEST indicates the effectiveness of an organization’s risk management program?
A . Inherent risk is eliminated.
B. Residual risk is minimized.
C. Control risk is minimized.
D. Overall risk is quantified.
Answer: B