Which of the following best describes this type of meeting?

A meeting agenda included the following items:

. Review the goals of the project.

. Review the progress of the project.

. Discuss if the project is ready to move forward.

Which of the following best describes this type of meeting?
A . Stand-up
B . Monthly status
C . Gap analysis
D . Gate review

Answer: D

Explanation:

A gate review is a type of meeting that evaluates the completion and quality of a project stage and decides whether the project can proceed to the next stage. A gate review is a formal governance step that involves reviewing the goals, progress, risks, deliverables, and benefits of the project, and discussing if the project is still aligned with the business strategy and stakeholder expectations. A gate review can have different outcomes, such as go, kill, hold, recycle, or conditional go, depending on the assessment of the project status and viability123.

Reference = CompTIA Project+ Study Guide: Exam PK0-005, 3rd Edition, Chapter 9: Project Change Management, p. 323; Everything Project Managers Need To Know About Gate Reviews | monday.com Blog; Gate reviews: What to do and why you need them – Rebel’s Guide to Project Management; Gates and How to Operate Them – GenSight