Exam4Training

Which of the following best describes the Scrum Pillar "Transparency"?

Which of the following best describes the Scrum Pillar "Transparency"?
A . The whole process should be visible to everyone.
B. The process should be visible to the key stakeholders.
C. Significant aspect of the process must be visible to those responsible for the outcome.

Answer: C

Explanation:

Only significant aspects should be visible, not all the details. The process does not to be visible to

everybody in the world.

Latest PSPO-I Dumps Valid Version with 481 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Exit mobile version