Which of the following BEST describes the relationship between test planning and test execution? [K2]
A . Test planning ensures the level of detail in test procedures is appropriate for test execution
B . Test planning schedules test execution but does not assign resources
C . Test planning defines the overall approach to testing but does not schedule specific activities such as test execution
D . Test planning identifies test objectives related to scope and risk but does not define the level of detail for test procedures used in test execution
Answer: A