Which of The following best describes a risk that is deemed "unacceptable" to the organization?
A . A risk where likelihood and impact are high
B . A risk where inherent risk exceeds its residual risk
C . A risk where inherent risk exceeds the tolerance level
D . A risk where residual risk exceeds the tolerance level
Answer: D