Which of the following best describes a project that has a negative Net Present Value?
Which of the following best describes a project that has a negative Net Present Value?
A . A loss making project
B . A project that doesn’t make enough profit to pay the interest on the money borrowed to invest in it
C . A project that doesn’t make sufficient returns to fully compensate investors for the funds they invest in it
D . A project that will only start making profits after the present year has finished
Answer: C