Which of the following BEST describes a project issue?

Which of the following BEST describes a project issue?
A . An event that may or may not occur
B . An opportunity that occurs through change control
C . A problem that the project manager has to deal with on a day-to-day basis
D . A problem that must be escalated to the appropriate level of management for resolution

Answer: D