Which of the following benefits is associated with using the iterative model?
A . It can be tailored to the needs of the project and organization.
B . It does not require knowledge of all the requirements up front.
C . It correlates directly to the deliverables of software development.
D . It focuses on exploring options early by feedback through prototyping
Answer: B
Explanation:
The iterative model benefits projects by allowing development to start without having all the requirements fully defined upfront. This model supports ongoing refinement through repeated cycles (iterations) of planning, development, and feedback. Each iteration builds upon previous work, allowing teams to adapt to changes and new information, which is particularly useful in projects with evolving requirements or high uncertainty.