Which of the following are valid settlement receives, when you perform settlement for an asset under construction, on a line item basis? Note: There are 2 correct answers to this questions.

Which of the following are valid settlement receives, when you perform settlement for an asset under construction, on a line item basis? Note: There are 2 correct answers to this questions.
A . Profit center
B. Fixed asset
C. Cost center
D. Functional area

Answer: B,C