Which of the following are true about the length of the Sprint? (Choose two.)
A . The length of the Sprint should be proportional to the work that is done in between Sprints.
B . It is best to have Sprints of consistent length throughout a development effort.
C . Sprint length is determined during Sprint Planning, and should hold the time it will take to code the planned features in the upcoming Sprint, but does not include time for any testing.
D . Sprint length is determined during Sprint Planning, and should be long enough to make sure the Development Team can deliver what is to be accomplished in the upcoming Sprint.
E . All Sprints must be 1 month or less.
Answer: BE
Explanation:
The correct answers are B and E, because these statements are true about the length of the Sprint. It is best to have Sprints of consistent length throughout a development effort, as this helps establish a reliable rhythm and cadence for the Scrum Team and the stakeholders. All Sprints must be one month or less, as this ensures that the Scrum Team can inspect and adapt frequently and deliver value incrementally.