Which of the following are required by Scrum? (choose all of those who apply)
A . Unit Tests.
B. Build automation
C. Release Burnup Chart.
D. Critical Path Analysis.
E. Refactoring.
F. None of the above.
G. Burndown Chart.
Answer: F
Latest PSD-I Dumps Valid Version with 166 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund