Which of the following are possible configuration steps when setting up the alert monitor in Advanced Planning? Note: There are 2 correct answers to this question.

Which of the following are possible configuration steps when setting up the alert monitor in Advanced Planning? Note: There are 2 correct answers to this question.
A . Create an object selection variant for priority-category-related alerts.
B . Assign the alert profile to the overall profile.
C . Create an object selection variant for production-planning-related alerts.
D . Assign the overall profile to the authorization profile.

Answer: B, C