Exam4Training

Which of the following are phases in an iterative project life cycle? 1) Concept 2) Feasibility 3) Deployment 4) Development

Which of the following are phases in an iterative project life cycle? 1) Concept 2) Feasibility 3) Deployment 4) Development
A . 3 and 4 only
B . 1, 2 and 3
C . 1 and 2 only
D . 2, 3 and 4

Answer: D