Which of the following are considered leading indicator metrics? (choose the best two answers)

Which of the following are considered leading indicator metrics? (choose the best two answers)
A . An item’s Work Item Age.
B. Service Level Expectation policy.
C. Current Work in Progress.
D. An item’s Cycle Time.
E. Monte Carlo simulations.

Answer: A,C

Explanation:

Work Item Age and current WIP are a leading indicators used during a Sprint (typically the Daily Scrum) to inspect and adapt the Sprint accordingly.