Which of the following are consequence of releasing a phase? NOTE: There are 2 correct answers to this question
Which of the following are consequence of releasing a phase? NOTE: There are 2 correct answers to this question
A . Predecessor phases are assigned the status locked
B . Lower-level tasks and checklist are release
C . Additional tasks cannot be added to the phase
D . The phase type is set to read-only
Answer: B,D
Latest C_S4PPM_1909 Dumps Valid Version with 80 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments