Which of the following appropriate tasks for the Test Analyst is performed during the test analysis phase?

Which of the following appropriate tasks for the Test Analyst is performed during the test analysis phase?
A . Review test estimates
B . Examine the test basis
C . Create a test execution schedule
D . Evaluate status against exit criteria

Answer: D