You are the Test Manager for a project to develop a web customer portal of a Pay-TV company that allows customers (with a smartcard and a set-top box) to purchase digital contents.
In the "select" page the system displays a dialogue where the customer can select the items (digital contents) he/she is interested in. In this page he/she can add one or more items to a shopping cart. An item consists of a product and a duration.
There are three types of products: Movie, sport and premium (movie and sport).
There are four possible durations: 1 months, 2 months, winter (from the beginning of January to end of March) and summer (from the beginning of July to end of September).
All the combinations of products and durations are allowed to define an item. Thus there are twelve possible items. A maximum of six different items can be added to the shopping cart at a time.
When the customer decides to check out he/she goes to the "purchase" page where he/she can pay the total amount of the shopping cart in three different ways:
– using a credit voucher
– using a credit already charged on the smartcard
– using a credit card (accepted credit cards are. Visa, MasterCard and Great Wall Card)
The customer can logout from both the “select” and “purchase” pages. In this case no purchase is made.
You decide to apply a blended risk-based and reactive testing strategy and the following is a subset of the exit criteria for system testing:
EXCR1- Each “critical” quality risk item must be covered by at least one test condition
EXCR2- Each “critical” requirement must be covered by at least one test condition
You are following a risk-based testing strategy. The test execution time is very limited.
Assume that all the product risk items require more or less the same level of test effort.
Which of the following answers describes the best execution schedule in this scenario?
K3 3 credits
A . 1- Test the acceptance of transactions coming from the IVR channel
2- Test the correct charge of the Smart Card with the required contents
3- Test the correct pre-activation of the Smart Card
4- Test the correct activation of the Smart Card
B . 1- Test the correct pre-activation of the Smart Card
2- Test the correct charge of the Smart Card with the required contents
3- Test the correct activation of the Smart Card
4-Test the acceptance of transactions coming from the IVR channel
C . 1- Test the correct activation of the Smart Card
2- Test the correct pre-activation of the Smart Card
3- Test the correct charge of the Smart Card with the required contents
4- Test the acceptance of transactions coming from the IVR channel
D . 1- Test the correct pre-activation of the Smart Card
2- Test the correct activation of the Smart Card
3- Test the correct charge of the Smart Card with the required contents
4- Test the acceptance of transactions coming from the IVR channel
Answer: D
Latest ATM Dumps Valid Version with 64 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund