Which of the following answers can be reasons for the Scrum Master to attend the Daily Scrum?

Which of the following answers can be reasons for the Scrum Master to attend the Daily Scrum?
A . To be able to track the Sprint progress.
B. It is not necessary for the Scrum Master to attend the meeting.
C. To support the Product Owner.
D. The developers have asked the Scrum Master to facilitate the Daily Scrum.

Answer: B,D

Explanation:

The Scrum Master does not have to attend the Daily Scrum unless he is asked to do so e.g. to facilitate the meeting.