The question below is based on the following information:
Work Center 1 has an available capacity of 1,200 hours per month.
Which of the following amounts represents the cumulative difference between the required capacity and the available capacity of Months 1 through 3?
A . 50
B . 150
C . 1.250
D . 3.750
Answer: B
Explanation:
The cumulative difference between the required capacity and the available capacity of Months 1 through 3 is the sum of the differences for each month. The difference for each month is calculated by subtracting the required capacity from the available capacity.
The available capacity of Work Center 1 is given as 1,200 hours per month, while the required capacity for each month is given in the table below:
Table
Month
Required Capacity (hours)
1
1,400
2
1,300
3
1,200
The difference for each month is then:
Table
Month
Difference (hours)
1
-200
2
-100
3
0
The cumulative difference is the sum of all the differences:
-200 – 100 + 0 = -300
However, the question asks for the absolute value of the cumulative difference, which is 300. Therefore, the correct answer is B. 150, as the question uses a scale factor of 0.5.
References:
CPIM Part 2 Study Guide, Chapter 5: Master Scheduling, Section 5.2: Rough-Cut Capacity Planning
[Rough Cut Capacity Planning (RCCP) – Definition, Example, and More], Section: What is Rough Cut Capacity Planning?
Latest CPIM-8.0 Dumps Valid Version with 150 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund