Which of the following activities still needs to be performed to complete the schedule?

By developing a project schedule, a PM has already validated the constraints, outlined the duration of the tasks and the phases, and confirmed the proper sequence and flow of the project.

Which of the following activities still needs to be performed to complete the schedule?
A . Allocate resources.
B. Determine the project budget
C. Develop a communication plan.
D. Establish baselines.

Answer: A

Explanation:

To complete the project schedule, the project manager still needs to allocate resources to the tasks and activities. This includes assigning personnel, equipment, materials, and other necessary resources to each task within the project. Proper allocation of resources helps to ensure that tasks are completed on time and within budget, and it also allows the project manager to identify potential bottlenecks, resource conflicts, or overutilized resources that may impact the project’s progress.

Latest PK0-005 Dumps Valid Version with 81 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments