Which of the following activities should the project manager perform NEXT?
A task on the critical path will not be completed on time. The project manager is reviewing both the schedule and the risk register to create a corrective action plan. The project completion date and quality of the deliverable cannot change .
Which of the following activities should the project manager perform NEXT?
A . Revise the project plan.
B . Update the issue log.
C . Request additional funding.
D . Issue a change request.
Answer: A