Which of the following activities is the Executive responsible for?
Which of the following activities is the Executive responsible for?
A . Ensure the desired outcome of the project is specified
B . Responsible for the benefits review plan
C . Assess and update the Business Case at the end of each stage
D . Responsible for the Benefits Review Plan post project
Answer: B