Exam4Training

Which of the following activities does the purchaser perform during the Scheduling Agreements in Procurement (BMR) scope item? Note: There are 2 correct answers to this question.

Which of the following activities does the purchaser perform during the Scheduling Agreements in Procurement (BMR) scope item? Note: There are 2 correct answers to this question.
A . Create purchasing info record
B. Post goods receipt for scheduling agreement
C. Display stock / requirements list
D. Maintain delivery schedule

Answer: B,D

Exit mobile version