Which of the following activities are important parts of the closing phase? (Select two).

Which of the following activities are important parts of the closing phase? (Select two).
A . Releasing resources
B . Locking risks
C . Updating stakeholder register
D . Closing contracts
E . Completing the work breakdown structure
F . Negotiating the next project

Answer: A,B

Explanation:

These are two of the key activities in the closing phase, as they involve finalizing the use of resources and resolving any remaining risks that may affect the project performance or quality.

Reference = CompTIA Project+ Study Guide1, Chapter 12: Closing Phase Activities