Which of the following activities are completed in the Realize phase of the SAP Activate Methodology? Note: There are 2 correct answers to this question
Which of the following activities are completed in the Realize phase of the SAP Activate Methodology? Note: There are 2 correct answers to this question
A . Demonstrate where to find business process documentation
B . Set up manual test cases in SAP Cloud ALM
C . Enter configuration values in SAP Central Business Configuration
D . Gather perceived change impact feedback
Answer: B, C
Explanation:
In the Realize phase of the SAP Activate Methodology for implementing SAP S/4HANA Cloud Public Edition, activities such as setting up manual test cases in SAP Cloud ALM and entering configuration values in SAP Central Business Configuration are completed. These steps are crucial for ensuring that the system is configured according to the business requirements and that all functionalities are thoroughly tested before going live.
References:
SAP Activate Methodology for SAP S/4HANA Cloud
SAP Cloud ALM and SAP Central Business Configuration guides