Which of the following activities are associated with the closing phase of a project? (Choose two.)
Which of the following activities are associated with the closing phase of a project? (Choose two.)
A . Risk mitigation
B . Archiving of project documents
C . Tracking of expenditures
D . Lessons learned
E . Quality assurance
Answer: B,D
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 338, 339