Which of the following actions should the project manager take NEXT?

A project manager realizes that a project will not be completed on time due to resource constraints.

Which of the following actions should the project manager take NEXT?
A . Trigger the contingency plan and communicate with the stakeholders.
B . Work with the functional managers to create a work-around.
C . Submit a change request to the change control board.
D . Transfer the risk by hiring a new vendor who was successful on a previous project.
E . Set up an escalation meeting with the sponsor.

Answer: C

Explanation:

Submit a change request to the change control board. The project manager should submit a change request to the change control board (CCB) if they realize that the project will not be completed on time due to resource constraints. A change request is a formal proposal to modify any aspect of the project, such as scope, schedule, cost, quality, or resources. A change request must be submitted to the CCB, which is a group of stakeholders who are authorized to review and approve changes. Submitting a change request can help to document the impact of the resource constraints on the project and seek approval for any corrective actions or preventive actions12