Which of the following actions should the project manager take?
An authorized change to a construction project was implemented. During the modification, the team identified a defect in which the change caused the building power output to be outside the KPPs.
Which of the following actions should the project manager take?
A . Submit a new change request.
B . Initiate the regression plan.
C . Add remediation to the schedule.
D . Accept the new power output.
Answer: B
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 294