Exam4Training

Which of the following actions should the project manager most likely take?

A developer recommends modifying an existing portion of code that is not part of the scope and is causing low performance on the current solution.

Which of the following actions should the project manager most likely take?
A . Ask a developer to create a change request.
B . Do nothing because recommendation is scope creep.
C . Ask a developer to implement the recommendation.
D . Communicate the change status.

Answer: A

Explanation:

The project manager should ask the developer to create a change request, which is a formal document that describes the proposed change, its benefits, costs, risks, and impacts on the project scope, schedule, budget, and quality. A change request is the first step in the change control process, which involves evaluating, approving, or rejecting changes to the project baselines. The project manager should not do nothing, because ignoring the recommendation could result in poor performance and customer dissatisfaction. The project manager should not ask the developer to implement the recommendation without following the change control process, because that could cause scope creep, which is the uncontrolled expansion of the project scope without proper authorization or adjustment of the project resources and objectives. The project manager should not communicate the change status before the change request is submitted and approved, because that could create confusion and false expectations among the project stakeholders.

Reference = CompTIA Project+ Study Guide: Exam PK0-005, 3rd Edition, Chapter 4: Project Integration Management1; CompTIA Project+ Certification Study Guide, 3rd Edition, Chapter 4: Project Integration Management2; What is a Change Request and How to Manage It3

Latest PK0-005 Dumps Valid Version with 81 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Exit mobile version