A contractor attended a project meeting that was exclusively for company employees.
Which of the following actions should the PM take?
A . Escalate to vendor management.
B . Consult the request for proposal.
C . Review the meeting cadence.
D . Reinforce the rules of engagement.
Answer: D
Explanation:
The rules of engagement are the guidelines and expectations that define the relationship between the contractor and the company. They may include topics such as communication, confidentiality, access, security, performance, and compliance. The project manager should reinforce the rules of engagement with the contractor to ensure that they understand and respect the boundaries and protocols of the company. This will help to avoid any potential conflicts, misunderstandings, or breaches of contract.
Reference = CompTIA Project+ Study Guide: Exam PK0-005, 3rd Edition, Chapter 7: Project Stakeholder Management, p. 239; Contractor Rules of Engagement – Cox Enterprises, p. 1; Legal Considerations for Engaging Contractors | LegalVision
Latest PK0-005 Dumps Valid Version with 81 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund