Which of the documents was likely missed or outdated?
During the early phase of a project, the requirements documentation was not approved. It was identified that the leader of a user party was not included in any of the requirements collection communications.
Which of the documents was likely missed or outdated?
A . Business Documentation
B. Stakeholder Register
C. Risk Register
D. Project Charter
Answer: B