Which of the Belbin’s team roles is most appropriate?

A project manager requires a team member to focus on the team’s objectives and draw out other team members.

Which of the Belbin’s team roles is most appropriate?
A . Shaper.
B . Monitor evaluator.
C . Specialist.
D . Co-ordinator

Answer: D