Which meeting should the Scrum Master attend (not facilitate)?
Which meeting should the Scrum Master attend (not facilitate)?
A . PO sync
B. lteration review
C. Scrum of scrums
D. Daly stand-up
Answer: C
Explanation:
Scrum Master should attend Scrum of scrums as participant, rest Iteration review and DSU is facilitated by SM.