Which maintenance statuses must be defined in SAP Materials Management before you buy a valued material for receipt into stock? There are 2 correct answers to this question.
Which maintenance statuses must be defined in SAP Materials Management before you buy a valued material for receipt into stock? There are 2 correct answers to this question.
A . Costing
B . Purchasing
C . Storage
D . Accounting.
Answer: B,D